NCEC classification and permit to establish

We classify your project, prepare the study its category needs and manage the NCEC application until the permit to establish is issued.

Request a proposal

Overview

We are an NCEC Type A licensed environmental consultancy that classifies your project and obtains its NCEC environmental permit to establish. The service is for developers, investors and plant owners starting a new activity, or expanding, modifying or adding to an existing one. We complete the environmental classification form, prepare the study your category needs and manage the application until the permit is issued.

Every new activity in Saudi Arabia needs an environmental permit to establish from NCEC, and so does every expansion, modification or added activity. The route depends on the category NCEC sets from your classification form: an environmental management plan for Category 1, an EIA for Category 2, or a scoping report followed by an EIA for Category 3.

As an NCEC licensed service provider we handle the whole route for you: the form, the baseline surveys, the study, the submission and the answers to NCEC’s comments.

NCEC classifies an activity by its expected environmental impact. It looks at the type and size of the activity, the energy it uses, depletion of natural resources, land use, the sensitive receptors around the site and the impact itself, including whether it is cumulative, how long it lasts and whether it can be reversed. Category 1 impact stays within the site. Category 2 is moderate and can be controlled. Category 3 is significant and may reach beyond the site.Permits reg. Art. 4(2) and (4)

The category is not fixed. You can ask NCEC to reclassify an activity with documented evidence of changes that reduce its impact, and NCEC may change the category based on the submitted study. NCEC’s chief executive also issues indicative lists that classify activity types.Permits reg. Art. 5(4) and Art. 4(3). Permit guide, controls section

Preparing the study itself? See our environmental impact assessment (EIA) service.

In brief, from our library

You apply through NCEC's electronic licensing system with the classification form, the investor ID or commercial registration, the site's national address and the fee. NCEC sets the category, then asks for the study that category needs: an EMP for Category 1, an EIA for Category 2, or a scoping report and EIA for Category 3. Studies and measurements must come from NCEC licensed service providers.NCEC guide LO-1-M-005-V01 for issuing and renewing environmental permits

Read the full guide: How is an NCEC environmental permit issued?

When you need it

  • You are starting a new activity, expanding or modifying an existing one, or adding an activity on the same site.NCEC guide LO-1-M-005, controls section
  • Your Category 1 project is within 500 m of sensitive areas or receptors, so NCEC asks for a detailed EIA instead of an EMP.NCEC guide LO-1-M-005, technical requirements
  • Your project is Category 3, which starts with a scoping report that NCEC must approve before the EIA.NCEC guide LO-1-M-005, technical requirements

What is included

  • Project screeningThe activity, its scale, its stages and the sensitive areas and receptors around the site, reviewed before the form is filed.
  • Phasing reviewThe full build-out and every planned phase defined up front, so the project is classified as a whole.
  • Support activitiesCamps, batch plants and other support activities checked to confirm whether they sit inside the main permit.
  • Reclassification requestsWhere design changes reduce the impact, the evidence NCEC needs to consider a lower category.
  • NCEC presentationsIf NCEC calls you to present the study, our authors attend with the field data and responses to comments.
  • Other approvalsA list of the other authority licences the project still needs alongside the NCEC permit.
  • Permit conditions handoverEach condition of the issued permit explained to your construction team before mobilisation.

What we deliver

  • Classification form and category adviceWe screen the project against NCEC’s criteria before anything is filed.
  • Baseline surveysAir, noise, water, soil and ecology, by our own field teams.
  • Environmental management planFor Category 1 projects.
  • Scoping report and EIAFor Category 2 and Category 3 projects.
  • Submission and NCEC commentsFiled through NCEC’s electronic system, with every comment answered until approval.

How we work

  1. Screen the project

    We review the location, activity and scale against NCEC’s classification criteria and plan the timeline and budget.

  2. File the classification form

    NCEC decides the category within 10 working days of the form.Permits reg. Art. 5(2)(b)

  3. Prepare the study

    Our team writes the EMP, the EIA, or the scoping report and then the EIA, from our own survey data.

  4. Review and decision

    NCEC decides a Category 2 EIA within 30 working days and a Category 3 EIA within 60. A request for corrections starts a new review period.Permits reg. Art. 7(4)(b) and Art. 8

Sectors we serve

Frequently asked questions

How long is an NCEC permit to establish valid?

A permit to establish is valid for 3 years. For large projects that need long design and funding periods, NCEC may extend it by 2 years, but the request must be included in the EIA study. If construction has not started before the permit expires, you need a new application and an updated study, and fees already paid are not refunded.Permits reg. Art. 6, Second (8) and Art. 9(4) and (5)

How much does NCEC charge to review the classification form and studies?

The fees regulation sets ceilings of 500 riyals for the classification form, 1,000 riyals for a Category 1 environmental management plan, 10,000 riyals for a Category 2 EIA, and 13,000 to 275,000 riyals for a Category 3 EIA depending on the project’s capital cost. NCEC fixes the actual amounts in its own charter within these ceilings.Fees reg. Art. 3(1) and Appendix 1

Can I split my project into phases to stay in a lower category?

No. NCEC may reject an EIA, or cancel an earlier approval, if a project is split into staged studies in a way that prevents correct classification, even where some parts already hold a permit to establish. Phased construction is not banned as such. The safe course is to assess the full build-out in one study and show the phasing inside it.Permits reg. Art. 9(2)

What is the fine for starting construction without a permit to establish?

Starting construction without a valid permit to establish is fined 5,000 riyals for Category 1, 20,000 riyals for Category 2 and 50,000 riyals for Category 3 activities. The same amounts apply to a modification or addition made without NCEC approval. A 1446H ministerial decision kept these amounts and classed every violation in the table as serious.Permits reg. Art. 11, Table 2 (2024), items 3 and 5. Decision 15029124 (1446H)

Can I object if NCEC refuses my permit?

Yes. NCEC may refuse to issue a permit to establish, but the refusal must be justified. You may object to NCEC’s decisions on environmental permits in writing within 15 working days of notification, and objections received after that are not accepted. NCEC decides on the objection within 30 working days of receiving it.Permits reg. Art. 6, Second (10) and Art. 10(1) and (2)

Request a proposal

Send us the location and what you plan to build. We reply with the likely route, what it involves and a proposal.

Request a proposal

Guides on this topic

References

Show all 12 references
  1. NCEC guide LO-1-M-005, controls section
  2. NCEC guide LO-1-M-005, technical requirements
  3. Permits reg. Art. 5(2)(b)
  4. Permits reg. Art. 7(4)(b) and Art. 8
  5. NCEC guide LO-1-M-005-V01 for issuing and renewing environmental permits
  6. Permits reg. Art. 4(2) and (4)
  7. Permits reg. Art. 5(4) and Art. 4(3). Permit guide, controls section
  8. Permits reg. Art. 6, Second (8) and Art. 9(4) and (5)
  9. Fees reg. Art. 3(1) and Appendix 1
  10. Permits reg. Art. 9(2)
  11. Permits reg. Art. 11, Table 2 (2024), items 3 and 5. Decision 15029124 (1446H)
  12. Permits reg. Art. 6, Second (10) and Art. 10(1) and (2)
How to read these references 3 texts cited
  • Art. 7(4)(b) means Article 7, paragraph 4, item (b).
  • First, Second and Third are the numbered parts some articles are divided into. The Arabic texts write them أولاً، ثانياً، ثالثاً (meaning first, second, third).
  • Decision followed by a number is a ministerial or Council of Ministers decision. Most of the 1446H decisions replaced a regulation's penalty table.
  • H after a year marks the Hijri (Islamic calendar) year. 1446H ran from July 2024 to June 2025.

Every text we cite is listed on our regulations page.