28 penalty ranges from Table 3.1 of RCER-2025 Volume III, grouped by the Volume I section the clause sits in.
Table 3.1 gives a range for each clause of Volume I. The amount within the range depends on:
- The violation class the Royal Commission decides, from Class 1 (minor) to Class 6 (catastrophic).RCER-2025 Vol. III, 3 and 3.1.1, page 3
- Repeats within two years, which can raise the fine by a factor of 1.1 to the power (n − 1), where n is the number of incidents.RCER-2025 Vol. III, 3.1.2, page 3
- Self-reporting and cooperating, which multiplies the total by 0.75. Total fines may not exceed the maximum in MEWA’s environmental law.RCER-2025 Vol. III, 3.2 and 3.3, page 4
- Remedial costs, which are paid on top. Refusing to pay may lead to revocation of the EPO.RCER-2025 Vol. III, 3.4 and 3.5, page 4
Table 3.1 gives no currency. Volume III’s penalty notice form states fines in Saudi riyals (SR).RCER-2025 Vol. III, Appendix D, Penalty Notice of Non-Compliance, page 16 For how a fine is worked out and what to do when a notice arrives, read how the Royal Commission calculates a fine. NCEC fines are in the NCEC library.
- RCER-2025 Vol. III, 3 and 3.1.1, page 3
- RCER-2025 Vol. III, 3.1.2, page 3
- RCER-2025 Vol. III, 3.2 and 3.3, page 4
- RCER-2025 Vol. III, 3.4 and 3.5, page 4
- RCER-2025 Vol. III, Appendix D, Penalty Notice of Non-Compliance, page 16
| Violation | Fine | Reference |
|---|---|---|
| Permits and the regulatory system (Volume I, section 1) | ||
| Starting process construction without an EPC | 5,000 to 50,000 riyals (monthly) | RCER-2025 Vol. III, Table 3.1, clause 1.2.1, page 5 |
| Reconstruction, modification or expansion of an existing facility without an EPC | 200,000 to 500,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 1.2.2, page 5 |
| Late PAP submission for the EPC | 10,000 to 40,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 1.2.4, page 5 |
| Operating or commissioning without a valid EPO | 5,000 to 50,000 riyals (monthly) | RCER-2025 Vol. III, Table 3.1, clause 1.3.1, page 5 |
| Late EPO renewal | 50,000 to 110,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 1.3.6, page 5 |
| Modified facility without a new or amended EPO | 10,000 to 40,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 1.3.7, page 5 |
| Not operating in accordance with the EPO terms and conditions | 1,000 to 10,000 riyals per condition, in addition to the fine of the relevant clause | RCER-2025 Vol. III, Table 3.1, clause 1.3.9, page 5 |
| Environmental studies or field tests not conducted by an RC approved third party | 50,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 1.1.27a, page 5 |
| No detailed decommissioning plan before closure | 1,000 to 100,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 1.4.1, page 5 |
| No closure site impact assessment by an RC approved third party, or premises not restored | 200,000 to 500,000 riyals plus costs | RCER-2025 Vol. III, Table 3.1, clause 1.4.3, page 5 |
| Not notifying RC when process construction is approaching 30 days to final completion | 10,000 to 40,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 1.2.6, page 5 |
| Operating a modified or reconstructed facility without an amended or new EPO | 5,000 to 50,000 riyals (monthly) | RCER-2025 Vol. III, Table 3.1, clause 1.3.2, page 5 |
| Air (section 2) | ||
| Not following dust control measures during construction or site preparation | 10,000 to 40,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 2.3.9, page 5 |
| Missing annual stack emission testing | 10,000 to 100,000 riyals per annum per stack | RCER-2025 Vol. III, Table 3.1, clause 2.5.1, page 5 |
| Water and groundwater (section 3) | ||
| Discharging any water, including hydrotesting and dewatering water, to storm water channels or coastal waters without prior RC authorization | 200,000 to 500,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 3.3.3, page 6 |
| Discharging extracted groundwater without prior RC authorization | 200,000 to 500,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 3.11.3, page 7 |
| Contaminating groundwater | 200,000 to 500,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 3.11.1, page 7 |
| Using groundwater for any industrial purpose | 120,000 to 180,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 3.11.2, page 7 |
| New facility without the required permanent groundwater monitoring wells before operation | 120,000 to 180,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 3.11.4, page 7 |
| Missing the annual groundwater monitoring, the 90 day report or the 14 working day sampling notice | 120,000 to 180,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 3.11.5, page 7 |
| New facility without baseline groundwater monitoring and a baseline report before operation | 120,000 to 180,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 3.11.6, page 7 |
| Waste (section 5) | ||
| Industrial waste not treated or disposed of within 180 days | 120,000 to 180,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 5.4.1, page 8 |
| Soil (section 6) | ||
| Failing to report or falsifying soil contamination information | 10,000 to 1.0 million riyals | RCER-2025 Vol. III, Table 3.1, clause 6.2.5, page 8 |
| Noise (section 8) | ||
| Missing the annual perimeter noise survey and report | 120,000 to 180,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 8.2.2, page 9 |
| Noise at the boundary fence above the Table 8 limits | 5,000 to 10,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 8.2.1, page 9 |
| Not giving RC at least 14 days notice of noise monitoring | 10,000 to 40,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 8.2.5, page 9 |
| Reporting and record keeping (section 9) | ||
| Not reporting a hazardous material spill or release that may affect groundwater or the environment outside the plant | 200,000 to 500,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 9.2.7, page 9 |
| Missing the Gap Analysis Report or quarterly Compliance Status Reports | 30,000 riyals | RCER-2025 Vol. III, Table 3.1, clause 9.2.5, page 9 |