Royal Commission deadlines

34 time limits from RCER-2025 for facilities in Jubail, Yanbu, Ras Al-Khair and Jazan. RCER counts a day as a working day.

All three RCER-2025 volumes define a day as a working day, so a period of 60 days means 60 working days. Each row gives the volume, clause and page it comes from. To work out a date, use the deadline calculator. NCEC deadlines are in the NCEC library.

Royal Commission deadlines by topic
DeadlinePeriodReference
Permits and start-upRead the guide: When should we apply for the Royal Commission permit to operate?
Meaning of 'day' in RCER-2025 deadlines Working day RCER-2025 Vol. I, Glossary, Day, page ix
Submit the permit application package (PAP) to obtain the EPC for a new, reconstructed or modified facility At least 6 months before starting process construction RCER-2025 Vol. I, 1.2.4, page 5
Notify RC that process construction is approaching final completion 30 days before final completion RCER-2025 Vol. I, 1.2.6, page 5
Apply for the EPO with an updated PAP, the EIA and the EERP At least 60 days before the planned start of operations or construction completion RCER-2025 Vol. II, 1.3.2(i), page 4
Advance notice of start-up of a new or modified facility At least 30 days RCER-2025 Vol. I, 9.2.1, page 114
Formal notification of start-up once the EPO is received (monthly start-up updates are also required) Within 7 days of start-up RCER-2025 Vol. I, 1.3.1, pages 5 and 6
Validity of the Environmental Permit to Operate (EPO) 5 years from the date of issue RCER-2025 Vol. I, 1.3.6, page 6
Submit the EPO renewal form (all RC comments must be resolved before expiry) 6 months before EPO expiry RCER-2025 Vol. I, 1.3.6, page 6
Apply for a new or amended EPO for a modified facility (production or emissions up 10 percent or more, or new pollutants) 60 days before planned start-up RCER-2025 Vol. I, Table 9-A, page 118
Amended PAP for a major expansion or significant change to the process or scope after the EPO is issued 6 months in advance RCER-2025 Vol. II, 1.7.1, page 5
Waste, soil and closureRead the guide: We had a spill in a Royal Commission city. Who do we tell, and how fast?
Detailed decommissioning plan before facility closure 60 days before closure activities begin RCER-2025 Vol. I, 1.4.1, page 7
Company responsibility for remediation and reclamation issues after a reclamation certificate is issued 5 years after issue RCER-2025 Vol. II, Appendix L, 6.4, page L-26
Treatment or disposal of industrial waste at an RC approved waste management facility inside the industrial city, unless RC approves otherwise (the 180 days include storage at both the generating facility and the disposal facility) Within 180 days of the waste being generated RCER-2025 Vol. I, 5.4.1, page 91
Plan to investigate, treat and rehabilitate a contaminated site Within 60 days from the date of notification RCER-2025 Vol. I, 6.3.1, page 101
Detailed soil contamination investigation report Within 60 days after completing the investigation RCER-2025 Vol. I, 6.3.4, page 101
Remediation Execution Plan Within 30 days of completing the site investigation RCER-2025 Vol. I, 6.4.2, page 101
On-site remediation of contamination that exceeds the standards (clause 6.4.4 on the same page counts the 180 days from RC approval) Within 180 days from the incident notification date RCER-2025 Vol. I, 6.4.1, page 101
Reclamation or rehabilitation works after RC approves the reclamation plan Start within 60 days and complete within 180 days RCER-2025 Vol. I, 6.5.3, page 102
Reporting and monitoringRead the guide: What are the Royal Commission noise limits at our fence line?
Report planned start-ups, shutdowns and maintenance with potential for non-compliance 15 working days in advance RCER-2025 Vol. I, 9.2.6, page 115
Upsets and emergencies resulting in non-compliance: immediate report, then a written report Written report within one week of the event (Table 9-A also asks for an event summary within 24 hours) RCER-2025 Vol. I, 9.2.6, page 115, and Table 9-A, page 118
Spills or releases of hazardous materials that may affect groundwater or the environment outside the plant: immediate report, then a written report Written report within one week of the occurrence RCER-2025 Vol. I, 9.2.7, page 115
Notice to RC before stack emission testing, with the test plan At least 14 days before the test RCER-2025 Vol. I, 2.5.7, page 12
Stack emission test report Within 60 days of the test RCER-2025 Vol. I, 2.5.8, page 12
Perimeter noise survey report for facilities with equipment above 85 dBA (survey at least once a year) Within 30 days of completing the monitoring RCER-2025 Vol. I, 8.2.2, page 112
Retention of monitoring records At least 5 years from the date of the information RCER-2025 Vol. I, 9.3.3, page 116
Gap Analysis Report for existing facilities, followed by quarterly Compliance Status Reports Within 6 months of the effective date (each quarterly Compliance Status Report within one month after the end of the quarter) RCER-2025 Vol. I, 9.2.5, page 114, and Table 9-A, page 118
Notice to RC before noise monitoring (RC may witness it) At least 14 days before the monitoring RCER-2025 Vol. I, 8.2.5, page 112
Notice to RC before groundwater sampling (RC may witness it) At least 14 working days before sampling RCER-2025 Vol. I, 3.11.5, page 61
Groundwater monitoring results (sampling once a year unless the EPO says otherwise) Within 90 days after sampling RCER-2025 Vol. I, 3.11.5, page 61
Non-compliance and appealsRead the guide: How does the Royal Commission calculate an environmental fine?
After a Notice of Non-compliance: reasons for each violation and the immediate measures taken Within 10 days RCER-2025 Vol. III, 4.1.3, page 10
After a Notice of Non-compliance: compliance plan and schedule to prevent recurrence Within 20 days RCER-2025 Vol. III, 4.1.3, page 10
After a Notice of Non-compliance: pay the fine in full or appeal for reduction, suspension or waiver Within 30 days of receiving the notice RCER-2025 Vol. III, 4.1.3, page 10
Appeal to the CEO of the Royal Commission city against a violation notice (section 4.1.3 asks for payment or appeal within 30 days) Within 60 days from receipt of the violation notice RCER-2025 Vol. III, 4.2, page 11
Payment of fines after the CEO approves the appeal committee decision Within 30 days of the decision RCER-2025 Vol. III, 4.2, page 11