NCEC deadlines

96 time limits from the NCEC environmental regulations and the other national texts they sit with. How long the authority has to decide, and how long you have to submit, report, renew or object.

Each period is given as the regulation words it. Working days and days are not the same, so note which one applies. The authority column shows who the deadline involves: the body that must decide, or the one you submit to. The regulations page explains each short form. Facilities in Royal Commission cities follow the Royal Commission deadlines instead.

NCEC environmental deadlines by topic
DeadlinePeriodAuthorityReference
Permits and EIARead the guide: How long does NCEC take to review an EIA or scoping report?
NCEC decision on the environmental classification form (the clock starts after the fees are paid) 10 working days from the date of the form NCEC Permits reg. Art. 5(2)
Final classification decision after NCEC asks for corrected or missing information 10 working days from receipt of all required information or the amended form NCEC Permits reg. Art. 5(2)(b)
Extension of the classification decision for an activity not previously classified in NCEC lists Up to 10 additional days NCEC Permits reg. Art. 5(3)
NCEC review of a Category 2 EIA (after the fees are paid) 30 working days from receipt of the study NCEC Permits reg. Art. 7(4)
NCEC final decision on a corrected or completed Category 2 EIA 30 working days from receipt of the required information or amended study NCEC Permits reg. Art. 7(4)(b)
NCEC review of the Category 3 scoping report (after the fees are paid) 15 working days from receipt NCEC Permits reg. Art. 8, First (2)
Extension of the scoping report review. If NCEC sends no approval or comments by the end of the extension, the scoping report is deemed approved Up to 10 additional working days NCEC Permits reg. Art. 8, First (3)
NCEC review of a Category 3 EIA (after the fees are paid) 60 working days from receipt of the study NCEC Permits reg. Art. 8, Second (2)
NCEC final decision on a modified Category 3 EIA 60 working days from the date of the modified study NCEC Permits reg. Art. 8, Second (2)(b)
Validity of the environmental permit to establish 3 years NCEC Permits reg. Art. 6, Second (8)
Extension of the permit to establish for large projects that need long design and funding periods (the request must be included in the EIA) Up to 2 additional years NCEC Permits reg. Art. 6, Second (8)
Age limit for an EIA prepared before the permit guide was issued that NCEC may still accept (not if it was previously submitted to NCEC) Not more than 5 Gregorian years NCEC Permit guide, section 1 (b), technical controls
ConstructionRead the guide: How loud can a construction site be, and can we work at night?
Start construction before the permit to establish expires. After expiry a new permit is needed, with an updated EIA (Category 2 and 3) or a new classification form (Category 1) Before the permit to establish expires NCEC Permits reg. Art. 9(4)
Hours in which construction sites may exceed the zone noise standards, up to the Table 4 corrections (any other exceedance needs a prior NCEC permit) 7.00 am to 6.00 pm NCEC Noise reg. Art. 7(1)
Construction noise correction allowed above the zone standard, by duration of the construction activity Up to 2.5 hours: 10 dB. From 2.5 to 8 hours: 5 dB. Over 8 hours: 0 dB NCEC Noise reg. Art. 7, Table 4
Daytime and night-time periods used for the noise standards Daytime 7.00 am to 8.00 pm. Night-time 8.00 pm to 7.00 am NCEC Noise reg. Art. 1
NCEC decision on a noise permit to temporarily exceed the noise periods or limits (after the fees are paid) 5 working days from registration of a complete application NCEC Noise reg. Art. 10(2)
Extension of the noise permit decision period Up to 5 additional working days NCEC Noise reg. Art. 10(2)
Operation and auditsRead the guide: When is an environmental audit study due, and what does NCEC check?
Validity of the environmental permit to operate (set by NCEC for each activity) 3 to 6 years NCEC Permits reg. Art. 6, Third (7)
Environmental audit study for renewal of the permit to operate, Category 2 and 3 activities Every 3 years NCEC Permits reg. Art. 6, Third (6)
Application to renew the permit to operate 30 days before the permit expires NCEC Permit guide, section 5 (h)
Environmental measurements and analyses after start-up, for activities that held a permit to establish (undertaking given at the permit to operate stage) Within 3 months of starting operation NCEC Permit guide, section 7-2-3 (b)
Corrective action plan for measures that cannot be implemented immediately after an NCEC inspection 30 days from publication of the inspection results NCEC Audit reg. (1446H) Art. 4, Third (1)
NCEC decision on the corrective action plan 15 working days from receipt NCEC Audit reg. (1446H) Art. 4, Third (2)
Extension for developing the corrective action plan (a preliminary plan must accompany the request) Up to 30 additional days NCEC Audit reg. (1446H) Art. 4, Third (4)
NCEC review of an environmental audit study submitted with the renewal application 30 days from receipt NCEC Audit reg. (1446H) Art. 5, Second (2)
NCEC final decision on a revised audit study 30 days from receipt of the revised study NCEC Audit reg. (1446H) Art. 5, Second (2)(b)
Extension of the NCEC review period for an audit study, with notice to the person Up to 15 days NCEC Audit reg. (1446H) Art. 5, Second (3)
Validity of the environmental compliance certificate Same as the validity of the environmental permit NCEC Compliance certificate guide, section 11 (4)
Collection of the annual financial dues for the permit to operate First quarter of each calendar year, or in parts of the year NCEC Fees reg. Art. 4(6)
Validity of the closure approval acknowledgement (NCEC may extend it depending on the activity size) 120 days NCEC Permit guide, section 11-1
Earliest date to apply for closure approval (all hazardous and non-hazardous waste must already be disposed of through licensed providers) At least 30 days after the last production run NCEC Permit guide, section 11-2 (a)
First measurements on all stacks of a new facility Within 120 days of establishment or 40 days of reaching the target production rate, whichever comes first NCEC Air reg. Art. 5, Fourth (3)(c)
Stack measurements for point sources that are not under continuous monitoring Every year NCEC Air reg. Art. 5, Fourth (1)
Measurement of every stack where NCEC approves testing a reduced number of identical stacks each year At least once every 4 years NCEC Air reg. Art. 5, Fourth (3)(b)
Notice to NCEC before measuring primary sources that are not under continuous monitoring 30 working days before the measurements NCEC Air reg. Art. 5, Fourth (8)
Report on measurements of primary sources that are not under continuous monitoring Within 40 working days of the measurements NCEC Air reg. Art. 5, Fourth (10)
Operating procedures for continuous emission monitoring systems submitted to NCEC Within 90 days of installing the monitoring systems NCEC Air reg. Art. 5, Third (10)
Continuous monitoring audit report submitted to NCEC 40 working days from completion (reference method) or 10 working days (other methods) NCEC Air reg. Art. 5, Third (16)
Repair of defects found in a continuous monitoring audit Within 10 working days of the report NCEC Air reg. Art. 5, Third (17)
Retention of point source records on start-up, shutdown, failures, tests, calibration and maintenance (NCEC may increase the period) At least 5 years NCEC Air reg. Art. 5, Fifth (1)(a)
Emergency or shutdown exceedance of point source emission standards that becomes subject to NCEC evaluation (firefighting is exempt at all times) Beyond 6 hours NCEC Air reg. Art. 5, First (6), Table 1
NCEC decision on a temporary exemption from point source emission standards (after the fees are paid) 15 working days, extendable by 5 working days NCEC Air reg. Art. 5, Second (4)
NCEC decision on an ambient air quality monitoring network licence 15 working days, extendable by 10 working days NCEC Air reg. Art. 4, Third (5)
Repair of VOC storage tank defects found by NCEC Within 30 working days of the inspection NCEC Air reg. Art. 6, Third (11)
Retention of noise monitoring data by permit holders required to monitor noise At least 3 years NCEC Noise reg. Art. 8(2)
Water and dischargesRead the guide: Where can dewatering water go: the sea, a storm drain or the sewer?
NCEC decision on a discharge permit, a temporary exceedance permit or an ambient water monitoring licence (after the fees are paid) 30 working days from meeting all application requirements NCEC Aqueous reg. Art. 8, First (2)
Extension of that decision period Up to 10 additional working days NCEC Aqueous reg. Art. 8, First (2)
Validity of a permit to discharge water into environmental media, including ground wells Up to 6 months, extendable by 4 months (the English text prints 'six (4) months' and the Arabic text says 4 months) NCEC Aqueous reg. Art. 8, Fourth (3)
Validity of a permit to temporarily exceed the treated wastewater standards Up to 6 months, extendable by 4 months NCEC Aqueous reg. Art. 8, Third (3)
Validity of an ambient water monitoring network licence Up to 3 years NCEC Aqueous reg. Art. 8, Second (5)
Capacity of emergency containment tanks at activities that treat wastewater or send it to central treatment plants Volume of wastewater treated in 36 hours NCEC Aqueous reg. Art. 7(2)
Retention of wastewater monitoring and analysis records (NCEC may extend by 5 years) At least 5 years NCEC Aqueous reg. Art. 6, Fourth (5)
Report any exceedance of the discharge standards to NCEC and stop the source Immediately after detection NCEC Aqueous reg. Art. 6, Fourth (4)
Decision on a licence under the marine and coastal regulation by the competent authority (NCEC, the National Center for Wildlife or the Red Sea coral reef and turtle foundation, each within its mandate), other than a marine hunting licence 30 working days from meeting all requirements, extendable by 10 working days NCEC Marine reg. (1448H) Art. 7, Second (2)
Notify NCEC of any oil spill, release of harmful substances, loss of cargo, or accident that may have an environmental impact in the marine or coastal environment, and start containment Immediately on learning of it NCEC Marine reg. (1448H) Art. 4(5)
Warning period to correct a non-serious marine or coastal violation before the fine (unlicensed Article 7 activity, unlicensed monitoring networks, late activity data) 30 days Competent authority Marine reg. (1448H) Table 1, rows 43, 48 and 49
Decision by the National Center for Wildlife on a marine hunting licence 10 working days from meeting all requirements, extendable by 5 working days National Center for Wildlife Marine reg. (1448H) Art. 7, Fourth (3)
Soil and rehabilitationRead the guide: What if we find contaminated soil during excavation?
Rehabilitation plan for Category 1 activities designated by NCEC at classification 30 working days from the classification decision NCEC Rehab reg. Appendix 1, First
NCEC review of that Category 1 rehabilitation plan 15 working days from receipt (revised plan: 5 working days) NCEC Rehab reg. Appendix 1, First
NCEC review of a rehabilitation plan included in a Category 2 or 3 EIA or in an audit study Within the EIA or audit study review period NCEC Rehab reg. Appendix 1, First
Submit or update a rehabilitation plan after an incident that causes degradation, or on NCEC request after an inspection or audit 10 working days NCEC Rehab reg. Appendix 1, First
NCEC decision on that rehabilitation plan 5 working days (revised plan: 5 working days) NCEC Rehab reg. Appendix 1, First
Submit a remediation plan after a pollution incident during establishment, operation or closure, or on NCEC request 10 working days NCEC Rehab reg. Appendix 1, Second
NCEC decision on a remediation plan 10 working days (revised plan: 5 working days) NCEC Rehab reg. Appendix 1, Second
Inform NCEC when soil pollution is detected during an activity As soon as it is detected (no number of days is set) NCEC Soil reg. Art. 7(7)
Objections and penaltiesRead the guide: How do I object to an NCEC decision or fine?
Written objection to an NCEC decision on an environmental permit (late objections are not accepted) 15 working days from notification NCEC Permits reg. Art. 10(1)
NCEC decision on a permit objection 30 working days from receipt NCEC Permits reg. Art. 10(2)
Written objection to an NCEC decision on a rehabilitation plan (incident or NCEC request) or a remediation plan (late objections are not accepted) 10 working days from notification NCEC Rehab reg. Appendix 1, First and Second, item 3
NCEC decision on that objection 10 working days from receipt NCEC Rehab reg. Appendix 1, First and Second, item 4
Objection to a penalty imposed by the competent authority, filed with the Committee Under the Committee rules. The 1446H regulation sets no period NCEC Violations reg. (1446H) Art. 6
Challenge to a Committee decision before the administrative court Allowed. No deadline in the official sources checked NCEC Env Law Art. 39(4)
Payment of compensation set by the competent authority 90 days from the notice date NCEC Violations reg. (1446H) Art. 5(2)
Violator's commitment in the violation report to appear before the branch or office Within 15 days NCEC Violations reg. (1446H) Appendix 1
Maximum suspension of a licence or permit as an administrative penalty Not exceeding 6 months NCEC Env Law Art. 38
Recidivism period in which committees may double the fine and the suspension Within 1 year from the date the previous penalty decision becomes final NCEC Env Law Art. 38
Precautionary suspension of an activity to avert an environmental disaster, ordered by the Minister or the chairman of the competent authority (referral to the court or committee within 5 days) Not exceeding 15 days NCEC Env Law Art. 44
Objection to an NCEC decision rejecting a self plan for emergency preparedness and response (late objections are not accepted) 10 working days from the date of the decision NCEC Emergency reg. Art. 4, Second (4)
NCEC decision on that objection 15 working days from receipt, extendable by 5 working days NCEC Emergency reg. Art. 4, Second (5)
Emergency plan objection treated as not accepted if the objector has not been notified of NCEC's decision on it After 15 working days (the text counts from the issue of the decision) NCEC Emergency reg. Art. 4, Second (6)
Decision on an objection to the refusal to issue or renew a licence under the marine and coastal regulation (the text sets no deadline for filing the objection) 30 working days from submission of the objection Competent authority (the text says 'the Centre' decides) Marine reg. (1448H) Art. 7, Second (5)
Court or Committee decision on whether a precautionary suspension continues Within 10 days of referral Competent court or the Violations Review Committee Env Law Art. 44
Service providersRead the guide: Who is allowed to prepare my EIA, EMP or monitoring report?
NCEC decision on a service provider licence application 20 working days from completion of all licence requirements NCEC SP reg. (1446H) Art. 6(5)
Extension of the licence decision period Up to 10 additional working days NCEC SP reg. (1446H) Art. 6(6)
Validity of a service provider licence Up to 3 years, set by activity size and classification NCEC SP reg. (1446H) Art. 6(7)
Service provider licence renewal application At least 3 months before the licence expires NCEC SP reg. (1446H) Art. 6(10)
NCEC decision on a request to upgrade the classification or add or delete service types 15 working days from a complete application NCEC SP reg. (1446H) Art. 7(4)
Validity of the individual professional licence for an environmental specialist 3 years NCEC Accreditation guide, Art. 3, First
EmergenciesRead the guide: Do we need an environmental emergency preparedness and response plan?
Notify NCEC and the relevant authorities of any environmental incident, whatever its size or type (also applies to operators of marine vessels) Immediately on learning of it NCEC Emergency reg. Art. 6(2)
Submit or update the self plan for emergency preparedness and response after NCEC notifies you (period set by NCEC by the nature, size and location of the activity) Not more than 30 working days from notification, extendable by up to 30 working days NCEC Emergency reg. Art. 4, Second (1)
NCEC decision on a self plan (after the fees are paid) 30 working days from completion of the application NCEC Emergency reg. Art. 4, Second (2)
NCEC final decision on an amended self plan after a request for more documents or information 30 working days from receipt of the amended plan, extendable by 5 working days NCEC Emergency reg. Art. 4, Second (2)(b)
Self-audit of preparedness and readiness At least once a year NCEC Emergency reg. Art. 4, First (10)
Self-audit report submitted to NCEC Within 30 days of the end of the audit NCEC Emergency reg. Art. 4, First (10)
Action plan for corrective measures after an emergency or environmental disaster Within 30 working days of the end of the emergency NCEC Emergency reg. Art. 8(2)
Amend the corrective action plan in line with NCEC comments Not more than 30 working days, or as NCEC decides NCEC Emergency reg. Art. 8(3)